Backwoods Home Magazine
Subscribe to Backwoods Home Magazine print or Kindle editions
Office Hours Momday - Friday  8 am - 5 pm Pacific 1-800-835-2418

Facebook   YouTube   Twitter
Follow Us!




Features
 Home Page
 Current Issue
 Article Index
 Author Index
 Previous Issues
 Newsletter
 Letters
 Humor
 Free Stuff
 Recipes
 Print Classifieds

General Store
 Ordering Info
 Subscriptions
 Kindle Subscriptions
 ePublications
 Anthologies
 Books
 Back Issues
 Help Yourself
 All Specials
 Classified Ad

Advertise
 Web Site Ads
 Magazine Ads

BHM Blogs
 Behind The Scenes
 Massad Ayoob
 Ask Jackie Clay
 Claire Wolfe
 Where We Live
 Dave on Twitter
Retired Blogs
 Oliver Del Signore
 David Lee
 Energy Questions
 Bramblestitches

Quick Links
 Home Energy Info
 Jackie Clay
 Ask Jackie Online
 Dave Duffy
 Massad Ayoob
 John Silveira
 Claire Wolfe

Forum / Chat
 Forum/Chat Info
 Enter Forum
 Lost Password

More Features
 Meet The Staff
 Contact Us/
 Change of Address
 Write For BHM
 Privacy Policy

Retired Features
 Country Moments
 Feedback
 Links
 Radio Show





Rural Building
By Martin Harris

Issue #62
  


Q. We have just purchased 15 acres, and our question is how to install our septic system, how far away from the on-site stream and can we use cinder blocks?

A. The short, common-sense answer is that, with any sort of normal soils, a properly-functioning system with cinder (actually, these days, theyíre concrete) blocks or even zero-cost fieldstone could be installed as close to the stream as, say 100 feet.

The longer answer is that common sense may not be enough. Thatís because most states have very detailed requirements for septic system installation, ranging all the way from professional-engineers-only design to minimum septic tank size and offsets from streams and property lines, including everything from fairly elaborate soil tests to bureaucratic on-site installation inspection.

It happens that Vermont law still includes our so-called ď10-acre exemption,Ē which allows any landowner with at least that lot size to design and install any arrangement he/she wants, as long as no effluent can be observed crossing the property line. This exemption has been under severe pressure by anti-rural-development advocates in recent years and wonít survive much longer, but while it does it allows a rural homesteader substantial design freedom at mimimal installation cost. There may be similar acreage-based exemptions in other states.

Most states now have regulations prohibiting the use of site-built septic tanks using concrete blocks. They require instead factory-manufactured pre-cast concrete units, with minimum size ranging from 500 to 1000 gallons in which primary (anaerobic) bacterial treatment occurs. The effluent then flows by gravity to the typical perforated-plastic-pipe field, where runs of pipe are set into gravel trenches for secondary (aerobic) bacterial treatment to take place. From the holes in the pipe, the treated effluent then flows harmlessly through the gravel into the ground. Could you build a tank out of block, laid up in waterproof manner with mortar joints and surface parging, setting it on a fairly solid concrete slab so it wonít settle and allow cracks to open up? Sure, if the authorities will let you.

The authorities might even let you build a tank out of dry-laid block, no mortar, with the core holes set horizontally, allowing the effluent to seep immediately into the ground. Such construction used to be made out of fieldstone and was called a cesspool; the design basis was that both anaerobic and aerobic digestion could take place in the same container, and the final effluent would be just as clean as in the more modern two-step system. If you go this route, youíll most likely want to emulate the old-timers and build two or three cesspools, directing the sewage flow into one for a few years, while the others are allowed to ďrestĒ and the sludge build-up in the surrounding soil to biodegrade.

Whether itís to be cesspool or septic tank, the top should be a couple of feet below grade in northern climates so that bacterial action isnít slowed by low soil temperatures. There should also be a removable lid so that the indigestible sludge which builds up at the bottom of the tank and the organic mat at the top donít fill up too much of the tank volume. Pumping every five years is usually recommended. If your design calls for the septic tank flow to go to a tile field, remember that the field pipes should be less than a foot from ground surface, so that the aerobic bacteria can get oxygen. Youíll need either a sloping site or an electric pump to meet this design essential.

If you donít fancy digging every five years to get to the tank lid, install an access route which is exposed at the soil surface. My own tank set up is properly buried, but over the lid opening thereís a three-foot length of three-foot diameter concrete pipe, with the lid on top of that. To pump the tank we just step through the surrounding flowerbed, lift the lid, and drop the pump hose down the hole into the tank. Slick.


Comments regarding this article may be addressed to editor@backwoodshome.com. Comments may appear online in "Feedback" or in the "Letters" section of Backwoods Home Magazine. Although every email is read, busy schedules generally do not permit a personal response to each one.







 